Alerts the office's server sent to this phone. Tap one to open it. A weather
warning shows on the home screen only for today's jobsite, until every Done is tapped or its day has passed.
MEMOS FROM THE OFFICE
Memos come from the office and cannot be answered here. A memo stays on
the home screen until you open it and tap I've read this; the office sees who has confirmed.
📣 FROM THE OFFICE
JOBSITE
Not selected
WHAT WAS DONE — WALL · SECTION · ROW
This is the daily field log. The official drilled and
shotcreted counts are entered separately by a supervisor in the
Anchor Progress tile on the home screen.
JOBSITE
Not selected
0
ENTRIES
0
STANDBY TIME
0
MAN-HOURS
Standby is waiting time inside the crew's normal hours. It does not
add hours or change anyone's pay — it records how long the crew waited and why.
JOBSITE
Not selected
DRAFT
0
ON SITE
0
DAY HRS
0
WEEK HRS
WORKERS — TAP TOGGLE IF ON SITE, TAP NAME TO EDIT TIMES
CREW / DAY NOTE
THIS WEEK — SUMMARY
0
DAY HRS
0
WEEK HRS
0
MEN (WEEK)
HOURS BY WORKER — THIS WEEK
HOURS BY JOBSITE — THIS WEEK
ADD WORKER
WORKER LIST ()
JOBSITES · managed by the office
LICENSES & CERTIFICATES
CREW DAYS · approved days on your jobsites
MATERIAL
COMPANY DOCUMENTS
SAFETY
EXTRA WORK · SUPERVISOR ONLY
EQUIPMENT — SERVICE TRACKER
Calculator categories
Total concrete
0.00m³
No panels yet
WIDTH & HEIGHT UNITS · thickness is always inches
Enter width, height and thickness
Thickness is always in inches — the m/ft switch above only changes width & height.
Tip: press Enter after each number — the last one adds the panel and clears for the next.
PANELS
SEND THE TAKE-OFF
Total grout — all piles
0bags
Enter the pile details below
PIPE PILES
GROUT · from your estimate sheet
Added to the diameter, so 2" means a 1" ring of grout all round the pipe — same as your estimate sheet.
RESULT
SEND THE TAKE-OFF
Closest utility
—
Add the anchor and the utilities below
WHERE
ANCHOR ROW
Depth at the wall is the top row. Change it to check the rows below.
ADD A UTILITY
Fill in the anchor and the utility
UTILITIES
SEND THE REPORT
Angle from horizontal
—°
Tap START and rest the phone on what you are measuring
Slope
—
Rise : run
—
Sensor
off
HOW THE PHONE IS SITTING
SAVE THIS READING
A phone is a ±1–2° instrument. It is right for setting a drill and for a record of what was built — it is not a survey.
REACH & DROP
· how far in, how far down
READINGS
SEND THE READINGS
CAMERA ALIGNMENT AID
📷Start the rear camera and aim squarely at the open pipe end.
Camera off
Is End B the opposite end of the SAME PIPE as End A?
Camera and motion access stay off until you tap Start.
Aim at the open pipe end. If detection struggles, tap roughly inside the opening to move the search area. The orange TOP marker follows true physical up; the blue BOTTOM marker follows gravity.
Field alignment aid only — not a certified surveying instrument. Keep clear of moving equipment and never walk while looking through the camera.
VIRTUAL ALIGNMENT LASER
📷 Start the rear camera and aim at the beam mark and plate.
Camera off
Camera stays off until you tap Start.
Field alignment aid only. Visually verify the plate before welding. This is not a survey instrument.
LIFT & SLING PLANNER
POSITION CONVENTION Plate width runs along the member axis. Overlap is the portion of that width extending inward from the member end; the remainder extends beyond the end. Example: a 4 ft plate with 8 in overlap has its CG 1 ft 4 in beyond End A.
Attachments are modelled as solid steel plates. Offset attachments require a manual engineering review.
Enter the final installed angle, not the sling angle. Valid planning range: 0° to less than 85°.
Enter the effective loaded length from the hook connection centre to the pipe connection centre, including hardware only when it is part of that measured length. Auto Balanced finds valid pick locations and minimizes the higher estimated sling tension.
OPTIONAL CAPACITY CHECK
WLL comparison uses ideal static planar tension only. It does not certify a lift or account for dynamics, side loading, sling hardware, edge protection, or site conditions.
Planning aid only — a qualified rigger/lift supervisor must select and inspect rigging and approve the lift plan.
CORNER BRACE — LENGTH & CUTS
Measure along each wall, from the corner to the CENTRE of the plate, on the plate face. Type it the way the tape reads — 6'-4 1/2", 76", 193cm or 1943mm. A number alone takes the unit picked above.
BRACE MEMBER
The mitre goes across the side that lies flat in plan (the side you see looking down).
FIT-UP
CUT SHEET
Fabrication aid only. Both plates are taken at the same elevation. Check the plate positions on site before cutting.
Straight line, first to last
—m
Start the GPS and walk the line
Accuracy
—
Along the path
—
Area
—
GPS
A phone fix is good to a few metres at best. Stand still a few
seconds before marking — the reading settles. Fine for hoarding lines, access roads and rough
site layout; not for setting piles.
POINTS
SEND THE MEASUREMENT
—
—
Length
Type it the way the drawing or the tape says it.
Area
Shotcrete face, mesh, lagging.
Force & lock-off
Off the anchor schedule.
Strength & pressure
Grout and concrete.
Anchor load at this gauge reading
—kN
Pick the jack, read the gauge, type it in
JACK
GAUGE → LOAD
LOAD → GAUGE
· what to pump to
ADD ANOTHER JACK
· from its plate or cert
Load = gauge × effective area. A jack added by area alone uses the maker's
theoretical number — good to about 1%. If the jack has a calibration certificate, send it to
the office — a calibrated jack can be pushed to every phone with its measured table.
JOBSITE
Not selected
Marked-up photos
0saved
Take a photo, draw on it, send it to the office
Arrows and a word or two beat a paragraph. Mark what you mean, then send it.